Luca's pic

Battenkill Twin Rivers Farm Habitat Enhancement Project

Update: Phase 3/Twin Rivers Extension Project Work Complete - 2008
Work on the third phase of the Twin Rivers Farm Habitat Restoration poroject was completed in early September. During this phase of the project, an additional half-mile stretch of river was restored with the installation of large woody debris and slate structures similar to those installed downstream in the first and second phases completed in 2006-2007. Details on this year's work forthcoming. For more details, see the Batten Kill Watershed Alliance website.
Twin Rivers Farm Habitat Restoration Project Twin Rivers Farm Habitat Restoration Project
Twin Rivers Farm Habitat Restoration Project
Planning Under Way for Phase 3 - 2008
Plans are on the drawing board and the necessary permits and contracts are being secured and drawn up for the next phase of habitat restoration work in the Twin Rivers Farm Project. Building on the success and experiences gained in the earlier phases of the project, work on the next phase of the project is scheduled to begin in late summer/early fall of 2008. Work will begin in the reach of river upstream of the already restored sections. For more information, refer to the Batten Kill Watershed Alliance website. Additional details will be posted as they become available.
Twin Rivers Farm Habitat Restoration Project
Click to view the slide presentation showing prelimnary data from 2007. [NB: 24MB download]
Update on Phase 2 - 2007 -- Completed!
Work on Phase 2 was completed on Wednesday, September 19, 2007, with the anchoring of the last cover trees, seeding, mulching, and rehab of the upper landing and island (areas used by the crew for materials staging and for access the river for the purpose of the project.) According to Scott Wixsom, Biological Technician with the Green Mountain National Forest, "the project turned out very well, weather and water levels cooperated, no injuries sustained nor breakdown of equipment."

Special Recognition and Thanks

Aside from the multiple partner organizations involved, much support was received from many people before and during the project, but one group that stands out and often receives little recognition is the corps of various contractors who played a key role in making incredible things happen on the ground and in the water: including Dean and Noel from Dydo, Pat and Shawn Salo, Joe Nolan and Nate, Steve Morse, and Keith Squires. All very professional, dedicated, and hard working individuals.   A HUGE thank you for a job well done!

Twin Rivers Farm Habitat Restoration Project
Here's a breakdown of the materials used and the habitat structures installed in phase 2.
Twin Rivers Project Structures and Materials 2007 (Phase 2)
Structures installed Materials Used
Rootwad Stations 12 Large Rootwads 23 Small Rootwads 22
Slate Stations 19 Slate 53
Individual Cover Trees 10 Whole Trees 36
Rock Vanes 3 Boulders 38
Below are a few dozen preliminary photos of some of the installed structures taken 9.16.2007. We'll post more photos of the completed structures as soon as we have them. (For more details, refer to the Batten Kill Watershed Alliance website.
Battenkill Twin Rivers Farm Restoration Project, Phase 2, September 2007
































Installation of the Phase 2 cover and shelter structures begins Monday, Sept 10, 2007. See below for diagrams of the planned cover and shelter structures. These structures will consist primarily of root wads and tree trunks, but will also incorporate existing trees and large boulders. Stay tuned as we'll post photos of the installed structures in the near future.
The project partners have been hard at work over the winter, individually, and collectively. Two planning meetings for Phase 2 and beyond have been held to date - including one in Dec 2006 and another in March 2007. Tentative site design plans for Phase 2 are presented below. Please note, however, that these plans are tentative and have NOT yet been finalized or received final approval. Much depends on how the spring runoff affects the existing structures installed just upstream, in Phase 1. (See below for photos & diagrams from Phase 1.)
Below are two sets of drawings of the stretch of river that will be worked on in Phase 2. The first set represents the existing conditions prior to the beginning of the project. And the second set of drawings are a *preliminary* view of the planned in-stream structures that may be installed in Phase 2.
Existing conditions
BK_Phase2_pre_p5 BK_Phase2_pre_p6 BK_Phase2_pre_p7 BK_Phase2_pre_p8
Preliminary planned structures for Phase 2
BK_Phase2_plan_p5 BK_Phase2_plan_p6 BK_Phase2_plan_p7 BK_Phase2_plan_p8
Update on Phase 1 (completed 2006)
According to Steve Roy, Fisheries Program Manager for the Finger Lakes/Green Mountain National Forests, as of January 3, 2007:

"The habitat work at the Twin Rivers site is doing its job of creating excellent cover and refuge for trout. The structures have withstood several high water events including one bankful (channel forming) event. The channel is changing as expected by forming depositional areas near the banks and scour holes around the structures."
Work on Phase 1 has been completed.
Work on Phase 1 of the project began as scheduled on Monday, September 11 and wrapped up early on Friday, September 15, 2006. See below for images and video from the project site. More than 25 stream-bank an in-stream installations were placed. Most of the installations were created using a combination of large woody debris (root wads, large diameter tree trunks, and rock), were secured to the stream bank and existing trees using chain, re-bar and boulders. The stations were designed and laid out in such a way as to appear natural and as 'non-engineered' as possible. Several large slab rock structures were also placed mid-stream to provide additional cover from overhead predators. The images below show a sampling of the stream structures installed. Stay tuned for additional details regarding the plans for Phase 2 of the project, scheduled for implementation in 2007.
Battenkill Twin Rivers Farm Restoration Project, September 2006






(Video clip) Chris Alexopoulous of the Green Mountain National Forest, USFS gives a brief explanation of some of the work being done on the project.






















With work on it scheduled to begin September 11, 2006, this critical habitat enhancement and restoration project is the joint project of the following contributing partners:
For more details on this project refere to the following document: Battenkill Twin Rivers Farm Habitat Enhancement Project.
Below are preliminary drawings & diagrams of the planned in-stream structure.
lesko0001 lesko0002 lesko0003 lesko0004

Battenkill Twin Rivers Farm Habitat Enhancement Project - Project Site Plans & Drawings

Phase 1 -- 2006
Pre-project Diagram - Existing Conditions & Plans

Centerline Profile

Cross Sections

Site Map

Upstream Plan

Downstream Plan
Phase 2 -- 2007
Pre-project Diagrams - Existing Conditions & Plans

Centerline Profile & Cross Sections

Cross Sections

Site Map

Current Conditions - Upstream

Current Conditions - Downstream

Upstream Plan

Downstream Plan
space
TU SWVT | Join TU | TU National | Vermont TU | Contact Info | About Us - Mission & Bylaws | Sponsors | Website & Newsletter | Swap Shop | Extras!